Upcoming Strategic Investment Projects

BIW Strategic Investment Project Overview

BIW has developed a Strategic Facility Project that is designed to modernize the Bath shipyard layout and facilities. The project scope includes:

  1. Demolition and replacement of the current Trades Learning Center. (complete)
  2. Demolition of the current Maintenance Building, which includes twelve smaller buildings constructed on this site from 1911 to 1983, and construction of a new Kitting Terminal. (complete)
  3. Demolition of the existing Main Gatehouse and attached Security Guard Offices (including three smaller buildings constructed between 1899 and 1910) and construction of a new main gate. (complete)
  4. Demolition of the existing Assembly Building Tool Crib located inside the Assembly Building and construction of a new Tool Crib and Lunchroom. (complete)
  5. Pier Support Center (in-progress)

These projects are intended to modernize BIW’s material kitting and delivery processes and infrastructure and improve the shipbuilding worksites for mechanics. The following provides an overview of the history of those existing shipyard buildings being proposed for demolition to make way for the new structures listed above.

BIW Shipyard History

The Bath, Maine, waterfront along the Kennebec River experienced significant commercial development during the 19th century. In 1850, Water Street ran along the bank of the Kennebec River, and numerous commercial piers/wharfs extended eastward from Water Street out into the river. As more waterfront structures were added, the concentration of pilings disrupted and slowed the flow of the river, and the areas between/under these piers were filled by river silt deposits as well as by deliberate construction projects. The Bath Iron Works Ltd. shipyard was established in 1888 on the site of the former Goss Marine Iron Works shipyard. Located on Robinson’s Wharf at the foot of Union Street, west of Water Street and adjacent to the Union Street Wharf, the manufacturing facilities of the small BIW Ltd. shipyard were built on pilings or on land created by filling-in the river. Over the following decades, the shipyard prospered and was able to expand substantially to the north and south, eventually acquiring all the riverfront property from King Street (north) to Shaw Street (south) and inland as far as Washington Street. The section of Water Street that extended south of King Street has been incorporated into the shipyard. Since all of the existing shipyard buildings proposed for demolition as part of the BIW Strategic Investment Project are located on the east side of the former Water Street, the land under them was reclaimed from the river.

5. Pier Support Center

As BIW accelerates the DDG 51 Program shipbuilding rate, Pier 2 has become an essential location for execution of post-launch ship construction work. This pier, compared to Pier 4, has significantly less infrastructure to support this type of work. As an example, portable toilets are used as the primary bathroom for more than 600 mechanics working on a ship at that pier. To address this, BIW intends to demolish the existing Boiler Shop and replace it with what we are referring to as a Pier Support Center (~17,000 square feet footprint, four stories). This building will house mechanic space for trades heavily involved in waterborne construction, workshops, bathrooms, a centralized lunchroom, lockers and other provisions required to support the pier. In addition to this new building, a “Direct Pier Support” structure (~3,500 square feet footprint, two stories) will be constructed just adjacent to the pier, housing amenities needed to be more closely located to the ingress and egress points of the ship. Together, these two structures will set this pier up for an accelerated shipbuilding pace.

Pier Support Center
Figure 5.0 – New Pier Support Center Rendering

Boiler Shop History

As part of a concerted effort to expand shipbuilding capacity prior to World War II, BIW obtained land in 1941 that abutted the yard’s south property line. According to a City of Bath Street Map dated 1851, this property included the Houghton Shipyard and two adjacent wharfs, both identified as Houghton’s Wharf. The majority of the land was east of Water Street and extended south almost to Federal Street, with one small parcel on the west side of Water Street at the corner with South Street. The shipyard had been vacant/inactive since 1909.

In 1941, BIW constructed the Boiler Shop on this site. The facility was designed to support the assembly/erection of steam boilers for US Navy WW II destroyers, and it continued to be used to assemble boilers for steam-powered US Navy and commercial ships until 1980. The last Bath-built, steam-powered ship, Hull 401 Resolute (American Export Lines containership), was delivered February 22, 1980. The building has a steel frame on a concrete foundation, infilled with a 6-foot high, brick knee wall topped by continuous rows of glass windows on all sides, separated by one row of metal panels. Interior columns were designed to support two, 20-ton bridge cranes (w/ 5-ton auxiliary lift). In 1942, a new building, used as a propeller finishing shop was attached to the south side. This building was wood-framed, infilled with wooden siding, with individual windows on three sides. Another attached structure, which was used to fabricate non-structural, interior bulkhead panels (Nomex), was added on the west side in the 1990s. Today, the original Boiler Shop is sided with corrugated sheet metal and houses workshops for pipefitters and outside machinists. Although BIW is proposing to demolish the Boiler Shop to facilitate construction of the multi-story Pier Support Center, the attached adjacent buildings will be retained and upgraded.

Addressing Environmental, Historical and Archeological Concerns

Environmental Permitting and Storm Water Infrastructure

The Maine DEP permitting package is being assembled with specific project information and drawings. The permit package is expected to be submitted to the Maine DEP around October1, 2021. Permitting information for all of the above mentioned projects will be included. The Maine DEP will work with BIW to review the package and request additional information as necessary. The process is expected to take three to four months until issue of the permit.

In concert with the above mentioned projects, BIW plans to install storm-water treatment infrastructure at the AEGIS Navy Complex on Washington Street. BIW intends to finish the design of the storm-water treatment installation by the fall of 2021, and implement the installation by the fall of 2023.

Section 106 Process

Although the buildings proposed for demolition are owned by BIW and sit on BIW property, federal funds are being used for the facility upgrades. This triggers Section 106 of the National Historic Preservation Act of 1966, and it has been determined that the proposed undertaking will have an adverse effect on the buildings impacted by the upgrade. For these reasons, BIW has been actively working with the Navy to ensure that the Section 106 process is being followed and that required approvals are obtained from the Maine Historic Preservation Commission (MHPC) prior to proceeding with demolition and excavation. In addition, during the Section 106 process, Sagadahoc Preservation Inc. (“SPI”) has been invited to consult with BIW and the Navy regarding the potential historical aspects and impact of the facilities upgrades. SPI is a local organization whose mission is to preserve and maintain Bath’s fine architectural heritage through the promotion of stewardship, education and community outreach.

Involvement and Approval of the Maine Historic Preservation Commission and Archeological Resources

The Maine Historic Preservation Commission (MHPC) has determined that buildings proposed for demolition and excavation in conjunction with the facilities upgrade may be eligible for listing in the National Register of Historic Places due to their significance associated with World War II naval vessel production at BIW. To determine whether potential historic/archeological resources are present in the subsurface of the buildings and surrounding areas, BIW has undertaken a Phase I historic archaeological survey, which will be completed prior to any excavation/demolition work. This survey may yield findings including ship remains, trash pits, privies, wharf remains and historic building remains. This survey and an appropriate mitigation plan will precede the required approvals from the MHPC.

City of Bath and Maine Department of Environmental Protection (DEP) Involvement

BIW has consulted with the City of Bath regarding the proposed projects and will continue to work directly with the city on various aspects of the Strategic Facility Improvements including, but not limited to, site-plan reviews and building and demolition permits. Currently, the City of Bath Planning Board has reviewed and given approval for the AB Tool Crib project. Plans and scheduled meetings are underway to continue the approval process for the rest of the projects in the upcoming months.

In addition, conversations with the Maine DEP are underway. BIW is expecting to submit the required Site Location application to the Maine DEP in October. All abutters and the City of Bath will receive a paper notification by certified mail of the “Notice of Intent to File,” which notifies all neighbors that BIW will be submitting a permit application to the Maine DEP in order to move forward with its Strategic Facility improvements within 30 days of the actual final application submittal. A copy of the final application will be made available at the Bath City Hall for review and all questions regarding the application can be submitted to Robert Green at the Maine DEP. Permits are also being obtained as required by the Natural Resource Protection Act.

Comment Submission

The public and other parties interested in submitting comments about the project described in this web page should direct e-mail messages to: historicproperties@gdbiw.com.